August 21, 2020 Construction Update

Construction Update – August 21, 2020

Progress on the MS building has come upon a disappointing setback. Our current move-in date has been delayed until the end of September. There are two factors causing this most recent delay: 1) the installers for one of the sub-contractors have not honored their timeline commitments in spite of multiple follow-up attempts to get them to do so and 2) supply delays due to COVID-19.

For those of you in or affiliated with construction work, these types of delays may be familiar to you. There are several options I am considering to meet the needs of the school while awaiting the MS building completion. Please visit this page to receive updates along the way.